A Teignmouth boat hire operator has won a landmark victory confirming his legal right to use part of a district council-owned car park for winter boat storage and maintenance.

Peter Stenner of Teign Boat Hire has been using a small section of the Lower Point car park for this purpose since 1982, always during the October to May off-season.

He claimed that this entitled him to the legal right of ‘easement’, which authorises the use of another party’s land for a specific purpose.

Teignbridge District Council challenged this – but the Supreme Court eventually found that the council’s case didn’t hold water.

In the field of property law, the finding overturns more than two decades of established practice on easements. It’s likely to be held up as an example in other cases involving the use of another’s land for parking or storage.

Mr Stenner’s legal victory followed a lengthy legal wrangle, after his initial claim for ‘easement’ was rejected by a tribunal in 2024.

He appealed against the judgement, and when the appeal was dismissed by a second tribunal, he successfully applied for the case to be heard at the Supreme Court.

The court announced its decision on Wednesday, November 25, and Teignbridge District Council said in response that it’s now ‘reviewing the practical implications for the management of Lower Point Car Park, together with the court order, legal costs and any implications for other council-owned land’.

Cllr John Parrott, Teignbridge District Council’s Executive Member for Finance and Corporate, said:

"We accept the Supreme Court’s judgment and recognise that it provides important clarification of the law on easements.

“The council had previously succeeded before both the First-tier Tribunal and Upper Tribunal.

Given those decisions and the wider uncertainty in the law, the council considered it appropriate to respond to the appeal and obtain clarity about the rights affecting council-owned land.

“We recognise Mr Stenner’s long association with Teignmouth and will approach the practical next steps carefully and constructively.

“We will provide further information when we have considered the court order, costs, and what arrangements may be needed for the future management of the site."